Dubai Power Transmission Projects 2026: DEWA Hits AED 10bn, 65 Substations

Dubai power transmission projects 2026: DEWA substation and busbar illustration with AED 10bn grid investment figure

Dubai Electricity and Water Authority has confirmed that its cumulative investment in electricity transmission network projects now exceeds AED 10 billion, about USD 2.72 billion, and that 65 new 132kV substations are currently under construction. The announcement was made on 21 July 2026 by Saeed Mohammed Al Tayer, Managing Director and Chief Executive Officer of DEWA.

For procurement managers, EPC contractors and equipment manufacturers, the headline investment figure is not the useful part. The forward pipeline is. DEWA said it plans to issue tenders for more than 30 additional 132kV substations over the next three years, alongside 340 km of underground transmission cables and two 400kV substations. That is a dated procurement window in one of the most bankable utility markets in the Gulf, and it sits on top of 65 substations already in execution.

What DEWA Commissioned in the First Half of 2026

DEWA reported two distinct blocks of commissioned capacity for the six months to 30 June 2026. The figures below come from the utility’s own statement.

  • Eight 132kV substations commissioned, with a combined conversion capacity of 1,200 MVA, at a cost of AED 970 million.
  • 20 km of transmission cable extended as part of that same 132kV package.
  • One 400/132kV substation at Saih Al Dahal, inside the Mohammed bin Rashid Al Maktoum Solar Park, with 2,000 MVA of conversion capacity at a cost of AED 630 million.
  • 117 km of 400kV overhead transmission line built as part of the Saih Al Dahal scope.

Hussain Lootah, Executive Vice President of Transmission Power at DEWA, said the newly energised 132kV substations serve Madinat Hind 4, Al Khairan First, Al Layan First, Nad Al Sheba First, Sheikh Mohammed bin Rashid Gardens, Al Barsha South Fourth, Me’aisem Second and Al Manara. The Madinat Hind 4 substation was built specifically to supply national housing developments.

Why does a 402-substation network matter to suppliers?

DEWA closed the first half of 2026 with 402 transmission substations in service, of which 28 operate at 400kV and 374 at 132kV. The ratio is the point. Dubai has built a comparatively thin 400kV backbone feeding a very dense 132kV layer, and it is the 132kV layer that grows every time a new district comes online.

That structure has two consequences for anyone selling into the network. First, unit volumes are concentrated in 132kV class equipment rather than in extra high voltage plant, which changes the competitive field and the qualification burden. Second, because each district substation is a broadly repeatable design, DEWA can award in batches. It awarded 21 contracts in the first half of 2026 alone for 132kV substation construction, plus contracts covering 64 km of connecting 132kV cable, at a combined value of AED 3 billion.

Those awards span 15 districts including Al Barsha South, Al Jaddaf, Jebel Ali First, Airport City, Bu Kadra, Umm Suqeim First, Warsan and Zabeel Second. The spread tracks Dubai’s development map rather than any single mega project.

What Is Going to Tender Over the Next Three Years

DEWA set out three forward commitments. None carry published tender dates, so the schedule below should be treated as a scope statement rather than a calendar.

  1. More than 30 additional 132kV substations to be tendered, on top of the 65 already in construction.
  2. 340 km of underground transmission cable to be extended.
  3. Two further 400kV substations to be constructed.

Set against the AED 3 billion that 21 substations plus 64 km of cable attracted in one half year, a pipeline of 30 plus substations and 340 km of cable implies a multi-billion dirham programme. DEWA frames it against the Dubai Economic Agenda D33, a signal that funding is policy backed.

How does Dubai’s substation pipeline affect procurement planning?

Suppliers targeting this pipeline should work backwards from the technical profile of a repeatable 132kV district substation.

  1. Qualification lead time. DEWA works through approved contractors and suppliers. For vendors not yet listed, qualification rather than the tender is the critical path.
  2. Batch capacity. Awards land in groups, so factory slot availability across simultaneous substations matters more than unit price on one job.
  3. Cable route scope. The 340 km underground cable programme is a separate demand stream covering cable, joints, terminations, ducting and route testing.
  4. Solar park integration. Saih Al Dahal shows the programme is partly driven by renewable evacuation, raising the specification bar on protection, monitoring and power quality equipment.

Which Equipment Categories Absorb the Spend

A 132kV district substation plus its connecting cable route consumes a predictable equipment basket. The largest line items are power and auxiliary power transformers for substation applications, followed by the switchgear, structures and conductor scope covered under transmission line and substation infrastructure.

Beyond primary plant, the secondary systems scale with substation count rather than with capacity. Each bay requires numerical protection relays and control panels, and commissioning each new substation drives demand for high voltage electrical test equipment. Renewable evacuation from the solar park adds a further requirement for power quality and grid support solutions to manage harmonics and voltage regulation at the point of connection.

Frequently Asked Questions

How much has DEWA invested in Dubai’s electricity transmission network?

DEWA confirmed on 21 July 2026 that cumulative investment in electricity transmission network projects has passed AED 10 billion, equivalent to roughly USD 2.72 billion. The figure covers substation construction, underground cable installation and overhead line works delivered across the emirate under the utility’s long term network expansion programme.

How many transmission substations does DEWA operate?

DEWA operated 402 transmission substations at the end of the first half of 2026. Of those, 28 are 400kV substations and 374 operate at 132kV. A further 65 new 132kV substations and one 400kV substation were under construction at the time of the announcement.

What transmission tenders is DEWA planning?

Over the next three years DEWA plans to tender more than 30 additional 132kV substations, two 400kV substations and 340 km of underground transmission cable. The utility has not published individual tender dates, so suppliers should monitor DEWA procurement notices directly for issue and closing schedules.

What was commissioned at the Mohammed bin Rashid Al Maktoum Solar Park?

DEWA commissioned a 400/132kV transmission substation at Saih Al Dahal inside the solar park. It provides 2,000 MVA of conversion capacity and cost AED 630 million. The scope also included 117 km of 400kV overhead transmission line linking the solar park to the wider Dubai transmission network.

Why is Dubai expanding its 132kV network so heavily?

The 132kV layer connects bulk supply points to distribution feeders in individual districts. Dubai is adding residential, logistics and commercial developments faster than the existing network can serve them, so each new district generally requires its own 132kV substation and a dedicated connecting cable route.